Scope of Work: Dumas
Concepts In Building provided $1.15 Million worth of services
for general contracting, mechanical renovations and improvements.
|
|
Function
of Project:
|
Art
Museum
|
|
Architect:
|
Smith,
Hinchman & Grylls
|
|
General
Contracting:
|
Dumas
Concepts In Building
|
|
 |
|

|
|
Scope of Work:
Dumas
Concepts In Building along with Dumas Central Industries provided
and installed a scrap handling conveyor system to aid DTE Energy
in the sorting and recycling of its products.
|
|
Facility
Function:
|
Recycling
|
|
General
Contractor:
|
Dumas Concepts In Building
|
|
Conveyor
Engineering :
|
Dumas Central Industries
|
|
 |
|

|
|
Scope of Work:
DCIB was contracted to renovate, fabricate and install hydraulic
doors for the elephant building. The elephant restraint system
and exercise yard was also worked on.
|
|
Facility
Function:
|
Zoological
Park
|
| Design
Engineer : |
Animal
Restraint Company |
|
Construction
Manager:
|
Dumas Concepts In Building
|
|
 |
|

|
|
Scope of Work: Sprayscape
is a place to cool off during the summer months for residents
and guests of Plymouth.
Dumas
Concepts In Building
completed this 2600 square foot of mini-water park in the fall
of 2002. It features water cannons, Horse Charger, Froggy-O,
Daisy Mae, Water O’s and 12 ground sprays designed to accommodate
all ages and at no cost!
|
|
Facility
Function:
|
Recreation
|
|
General
Contractor:
|
Dumas Concepts In Building
|
|
 |
|

|
|
Scope of Work: Dumas
Concepts In Building provided renovations to the Mezzanine and
staff floor at the Bank One Headquarters in Detroit, formerly
National Bank of Detroit (NBD).
Approximately
40,000 square feet of ceiling in the mezzanine area was removed
and a new grid system was configured with accoustical tiles
installed. The remodeling of the lavatory facilities also took
place during the non-peak hours to minimize distruption of the
client's daily core business.
Later
phases of the staff floor renovation included the construction
of a gift shop, two conference rooms and the installation of
a new cafeteria.
|
| Facility
Function: |
Corporate
Headquarters in Detroit |
| Architect: |
Albert
Kahn Associates |
|
General
Contractor:
|
Dumas Concepts In Building
|
|
 |
 |
| Scope
of Work: Dumas Concepts In Building was the general contractor
for the erection of two new salt storage domes and the repair
of two existing domes. These domes are designed to house salt
for the road crews to keep the streets of Detroit snow and ice
free during the winter months. |
|
Facility
Function:
|
Storage
of road salt
|
|
General
Contractor:
|
Dumas Concepts In Building
|
|
Completion
Date:
|
June 1994
|
| |
|